New Mario G. Olmos Elementary School. Fresno. A new elementary school site located at
Chestnut and Kings Canyon road. Currently working on the site work on and off site. Picture above is the water tie - in to
the site crossing Chestnut avenue.
Kingsburg Elementary - Kingsburg, CA
The Kingsburg Elementary School for Kingsburg Joint Union Elementary School District valued
is at $12,500,000 and designed by Teter a+e. Harris Construction Co., Inc. is the construction manager and is currently
under construction. Project completion July 2007
Tulare
Joint Union High School District - Tulare, CA
The Tulare Joint Union High School District has selected Harris
Construction Co., Inc. as the Construction Manager for the New Tulare 3rd High School in Tulare, CA. Project is currently
completing preconstruction service phase. Project anticipated cost is ±$53,000,000. Completion estimated in June
2008, design by Darden Architects, Inc
New K-6 Ellis Elementary School - A brand new Elementary school site in Madera, California located
on Ellis street between Merced and Chapin streets. Architecture is by Mangini Associates out of Visalia, Ca. Project estimated
budget is $13,974,000.00. T3 Engineering will be installing a new Sewer line and Storm Drain line to the new site. The
total length of the trench is approximately 1 mile. Todd Plumbing, Inc. will be installing the projects Plumbing systems.
Click on picture for additional shots.